Cost and Funds > Cash Flow Module Configured Field Sources Is Grayed Out When a Project Is Synced Via Integration
(Doc ID 2410244.1)
Last updated on JUNE 04, 2019
Applies to:
Oracle Prime Cloud Service - Version 18.5 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
In Cost and Funds > Cash Flow > Settings
- > Planned Budget
- > Forecast
These fields are greyed out.
This happens with an imported project or a sync projects (via gateway)
EXPECTED BEHAVIOR
For Planned Budget and Forecast to be available
STEPS
The issue can be reproduced at will with the following steps:
- Import a P6 project or create a project via Integration or Gateway
- Create a project natively in Prime Projects
- Go to Cost and Funds > Cash Flow (select default spread options)
- Select the Preferences
- Notice on the import or integration project, the top 2 fields, Planned Budget and Forecast, are not editable
- Open the project created in Prime Projects
- Notice Planned Budget and Forecast are available
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Cause 1: |
Cause 2: |
Solution |
To address the issue with a project that is synced via an integration: |
To address the issue with a P6 project import: |
References |