PJO: Import Baselined Budgets Using FBDI Gives Multiple Warnings and Errors.

(Doc ID 2417382.1)

Last updated on JUNE 29, 2018

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.13.18.02.0 and later
Information in this document applies to any platform.

Symptoms

When Importing Budgets into PPM using the FBDI, the following warning is received:

The budget version was not set as baseline as the burdened cost was more than the funding amount. A working version for the budget was created.

The burdened cost 2255318 in project ledger currency for the budget period CONV_BUDGET must not exceed the award funding amount 0 that is allocated to the project and funding source ABC.

The following error was also seen with this warning:

The project currency amounts must be same as the planning currency amounts because the project currency and the planning currency are same.

The project ledger currency amounts must be same as the planning currency amounts because the project ledger currency and the planning currency are same.

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms