Why Does Physical % Complete Type Require Separate Updates to Activity % Complete, Remaining Duration, and Resource Actual Regular Units?
(Doc ID 2421309.1)
Last updated on NOVEMBER 05, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.5 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 17.9.0.0 and later
Information in this document applies to any platform.
Goal
When Physical % Complete type is used why do both Activity % Complete and Remaining Duration have to be updated separately?
Does the same business rule apply when using Physical % Complete in the Team Member application?
In Microsoft Project if actual units are updated to 10% then remaining duration is automatically updated, why doesn't P6 application do this when Physical % Complete is applied?