Physical Percent Complete Progress not rolling up to top task
(Doc ID 2432752.1)
Last updated on SEPTEMBER 11, 2020
Applies to:
Oracle Fusion Project Foundation Cloud Service - Version 11.12.1.0.0 and laterInformation in this document applies to any platform.
Symptoms
Physical Progress % field not updated automatically for top task after updating the physical % complete values manually for sub-tasks.
EXPECTED BEHAVIOR: Project Progress tracking (Physical Progress%) should be rolled up to Parent task
Also, following exceptions were observed in the Progress tab:
1. The Actual Quantity field cannot be correctly calculated
2. No rate was found for the non-labor transaction.
Changes
Cause