Baseline Date Fields Report Null Values When Using P6 Professional Cloud Connect
(Doc ID 2434861.1)
Last updated on AUGUST 12, 2022
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.12.6.0 to 18.2 [Release 17.12 to 18.2]Primavera P6 Enterprise Project Portfolio Management - Version 17.12.6.0 to 17.12.7.0 [Release 17.12]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When setting a baseline, the baseline dates are not populated.
EXPECTED BEHAVIOR
Expect baseline dates to be populated.
STEPS
The issue can be reproduced at will with the following steps:
- Log into P6 Pro Cloud Connect
- Copy a project.
- Assign this project as a baseline to a different project.
- Notice baseline dates are not populated.
Cause