Date Varienaces Are Showing Blank in a Project Report Even When There Are Baselines With Different Data.
(Doc ID 2485922.1)
Last updated on NOVEMBER 14, 2019
Applies to:
Oracle Primavera Cloud Service - Version 18.11 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR:
When running a report of Date Variance in the Schedule App. the fields for the Date Variances appear to have no data. I would think that as a calculated number field, they would have at least a zero in the column. The schedule in question has a Baseline stored and there is Variance between the Baseline and Current Schedule.
EXPECTED BEHAVIOR:
For the Report to show a value instead of being blank.
STEPS:
The issue can be reproduced at will with the following steps:
1. Setup a Project with a Baseline where the dates differ (so there is Variance).
2. Create and Run a Project Report for Date Variance. Add in the following
fields:
ID
Project Name
Status
Scheduled Finish Date
Scheduled Finish Date (Baseline)
Variance - Finish Date
Variance - Finish Date (Baseline)
Variance - Start Date
Variance - Start Date (Baseline)
Schedule Variance
Schedule Variance (Baseline)
BUSINESS IMPACT:
The issue has the following business impact:
Due to this issue, users cannot rely on Report data.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |