Symptoms

Commission for participant for Q3 is incorrect.
User had change the rate after Q2 had been paid and recalculated and now commission for Q3 is wrong.


STEPS
1. Create a True-up plan component "Specialty IC16"
    Navigator > Compensation Plans > Manage Plan Component > Incentive Formula : True Up = checked
2. Create transactions
3. Run calculation and check commission for Quarter 1, 2, and 3
4. Realized that the rate is wrong at participant level is wrong, change the rate and rerun calculation for Q2.
5. Recalculate Q3 and the commission amount is lower at $6456.34 than expected of $6475.44

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.