Error 'Field PhysicalPercentComplete may not be set to null' When Synchronizing a Project to P6 Using Primavera Gateway (Doc ID 2497417.1)

Last updated on APRIL 03, 2019

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.1 and later
Primavera Gateway - Version 18.2 and later
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 and later
Information in this document applies to any platform.

Symptoms

When attempting to transfer WBS data from a source project into Activity data in a target project, jobs fail because Gateway is not able to load the Performance Percent Complete Labor Units from the WBS into the Physical Percent Complete of the activity in the target project.  Most projects complete but some fail with the following error.

Field PhysicalPercentComplete may not be set to null

<ActivityResponse action="create" executed="none" status="error">
    <ObjectId>-100</ObjectId>
    <RealObjectId>225392</RealObjectId>
    <DetailedError>Field PhysicalPercentComplete may not be set to null.</DetailedError>
    <UDF action="create" executed="none" status="none">
        <TypeTitle>L3_StartDate</TypeTitle>
    </UDF>
    <UDF action="create" executed="none" status="none">
       <TypeTitle>L3_FinishDate</TypeTitle>
    </UDF>
</ActivityResponse>

 

The issue can be reproduced at will with the following steps:
1. Create a synchronization that maps WBS to Activity.
2. Map the WBS Performance Percent Complete Labor Units to the Activity Physical Percent Complete.
3. Run the synchronization.
4. The error occurs in the Update Destination step.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.