Symptoms

On : 11.12.1.0.0 version, Manage Project Costs-Allocate Project Costs

Expenditure transferred to projects having start date later than expenditure date


ERROR

'The Project is not active as of he Expenditure Item Date'

STEPS

The issue can be reproduced at will with the following steps:
1.The Oracle Time and Labor records imported /interfaced to a specific project number (ie: N1)
2. There are number of Expenditure Items (EIs). All the Items have EI Date in May-July 2017
Then  a mass adjustment was done on the transactions and transferred them to a new project (ie N2).

Target project (N2) start date was 01-Jan-2018 while the expenditures items dates of original project are in 2017. System allowed these adjustments.

The adjustment was done to a wrong target project. So, then tried to transfer the EIS from project Number N2 to a new Project number N3 whose Start Date is in Dec-2009
Though the transfer adjustment program ran fine, system didn’t do the adjustment.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.