Unifier Summary Sheet Dates Are Off By One Day After Synching From P6 (Doc ID 2509139.1)

Last updated on SEPTEMBER 13, 2019

Applies to:

Primavera Unifier Cloud Service - Version 17.1 and later
Primavera P6 Enterprise Project Portfolio Management - Version 17.7 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.1 and later
Primavera Gateway - Version 17.7 and later
Information in this document applies to any platform.

Symptoms

The actual start and actual finish dates for the Unifier Summary Sheet do not match P6. For example, the dates in the Unifier Summary Sheet appear as 04/15/18 for the actual start and 05/13/18 for the actual finish. The P6 dates are 04/15/18 for the actual start and 05/14/18 for the actual finish.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into Unifier
2. Navigate to the project that was synchronized and open the Summary Sheet  (Schedule Manager > P6 Summary Sheet)
3. The Actual Start and Actual Finish dates are incorrect

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!