Cost Scenario Is Rolling Up Assembly Under Different Work Definition Name Than the One Selected in the Scenario
(Doc ID 2564428.1)
Last updated on FEBRUARY 21, 2023
Applies to:
Oracle Fusion Cost Management Cloud Service - Version 11.13.19.04.0 and laterOracle Fusion Cost Management - Version 11.12.1.0.0 and later
Information in this document applies to any platform.
Symptoms
Cost scenario is rolling up assembly under different Work Definition than one selected in the scenario
On creating a new scenario with work definition selection criteria having work definition name defined as 'STD Main' the assembly 20-004 is rolling up the assembly also under the old work definition name 'Main (V#1)'.
EXPECTED BEHAVIOR
-----------------------
Cost scenario should be rolling up under the work definition provided.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a new cost scenario Supply Chain Execution > Cost Accounting > Task list > Manage Cost Scenarios
2. Provide the work definition name in 'Work Definition' drop down, save and close
3. Define the final assembly, and resources using Actions > Define Standard Cost and Define Resource Rate.
4. Navigate to Actions drop down and click "Roll-up Costs".
5. Roll-up completes with warning.
6. Click on Actions > View Rolled-up Costs
7. Click on 'Show Hierarchy Viewer"
Cause