Symptoms
On : 11.13.19.07.0 version, Inventory Management
ACTUAL BEHAVIOR
---------------
Business observed partial picking isn't happening when running pick release for work orders .They created work order#1 for finished good with 20 qty and generated movement request via 'Release and Pick Materials' by unchecking 'Pick a work order only if all eligible materials are available' flag. Movement Request number#123 generated for 13 items where only two items#A and B were allocated .Remaining 11 items weren't allocated and showing error 'The material sourcing process failed to create picking suggestions for line 1999901 of movement request#1' in Pick Materials Worker for the Work Orders report . As per them, it was working fine when they were in 19B and observed issue in 19C.
All the items were having operation pull supply type. Reviewed the picking rule 'YYYY' where 'Allow partial picking' was enabled. Picking rule 'YYYY' was assigned to inventory org#1 without any criteria. Picking rule YYYY was assigned at inventory org#1 parameter. Checked the inventory org#1 plant parameter where 'Include pull components for pick release' was enabled.
Observed that system isn't allocating quantity in the movement request report if the required qty from work order is greater than available onhand in sub inventory. If the required onhand from work order is less than available onhand in sub inventory, it is allocating in the movement request output
EXPECTED BEHAVIOR
-----------------------
System should allocate the onhand even if the required quantity wasn't available as unchecked 'Pick a work order only if all eligible materials are available' flag while creating movement request.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create work order
(N) Supply chain execution-> Work Execution->Manage Work orders
2. Click Release and Pick Materials
(N) Supply chain execution-> Work Execution->Manage Work orders
3. Movement request will be generated
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |