Transfer Price Schedules Not Calculating The Cross Charge Amounts Correctly
(Doc ID 2611215.1)
Last updated on NOVEMBER 15, 2019
Applies to:
Oracle Fusion Project Costing Cloud Service - Version 11.13.19.07.0 and laterInformation in this document applies to any platform.
Symptoms
On : 11.13.19.07.0 version, Manage Project Costs-Allocate Project Costs
ACTUAL BEHAVIOR
After cloning the environment , The Borrow and lent shows as Not applicable at the Expenditure Item Level (for specific expenditure IDs)
Actions - Borrow and Lent: - Reprocess Borrow and Lent Amount is not active
Actions - Borrow and Lent: Reprocess Cross-charge method is active
Transfer Price Schedules not calculating the cross charge amounts correctly.
The transfer price amount calculated is incorrect. Attached is the screenshot of all the details of the issues we are looking into.
The borrowed and lent amount is not calculating per markup of 0 but using a different markup which is on legal entity level and the 0 markup is on the lowest level organization as on the transaction
EXPECTED BEHAVIOR
Borrow and lent to be processed successfully as before cloning
STEPS
The issue can be reproduced at will with the following steps:
Try to process Borrow and lent transactions inside same Legal entity
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |