Symptoms

ACTUAL BEHAVIOR
---------------
Auto schedule does not work when using "expected finish"

When entering or changing the expected finish date of an activity, the project does not re-schedule, despite auto-schedule being enabled

EXPECTED BEHAVIOR
-----------------------
When entering or changing the expected finish date of an activity, the project will be reschedule.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6 client and open a project
2. Press F9 and then option
3. Tick 'Use Expected Finished Dates' and "Schedule Automatically when a change affects the dates"
4. Close the schedule window
5. Add expected finish to "activity A" - auto schedule does not activate
6. Tick "started" on "activity B" and adjust the date - Auto schedule then adjusts activity A and activity B.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot see project auto schedule.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.