My Oracle Support Banner

Project Forecast Generated From Financial Project Plan Progress Has Incorrect ETC Spread (Doc ID 2640103.1)

Last updated on FEBRUARY 18, 2020

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.13.19.07.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.13.19.07.0 version, Control Project-Manage Project Forecast

ACTUAL BEHAVIOR
Project forecast generated from financial project plan progress has incorrect ETC spread amounts
 
EXPECTED BEHAVIOR
Project forecast generated from financial project plan progress to have ETC spread amounts.

STEPS
Physical Percent Complete Calculation Method: Manual Entry
ETC Method: Remaining plan

Primary Physical Percent Complete Basis: Cost

1. Create financial project plan with resource assignments / periodic plan amounts (accounting period).
2. Baseline plan.
3. Accumulate actuals.
4. Create progress report.
5. Publish progress report and generate forecast.
6. Review forecast; forecast ETC amounts are not spread in proprtion with the financial project plan.
 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.