My Oracle Support Banner

Expected Finish Date Cleared After Scheduling Project (Doc ID 2645750.1)

Last updated on MARCH 09, 2020

Applies to:

Oracle Primavera Cloud Service - Version 20.2 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Expected Finish date field in Activity Details cleared when project is scheduled.

EXPECTED BEHAVIOR

Expect Expected Finish field in Activity Details to remain after scheduling project.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into OPC.
  2. Schedule | Activities.
  3. Create activity.
  4. Add an Expected Finish date in Activity Details.
  5. Schedule project. Note that Finish Date is changed to reflect Expected Finish date, however, this field has been cleared in Activity Details.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.