Symptoms

It has been noted that the Cash Flow curves are not pulling dates from the Unifier Schedule Sheet as expected. An attempt was made to change from a standard calendar to a custom calendar. However the Project/Shell is not pulling schedule dates into the cash flow or forecasting spend. 


EXPECTED BEHAVIOR
-----------------------
Expecting that when viewing the Cash Flow curve the From Dates/To Dates will be populated as configured in the Schedule Sheet.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Log into the Unifier environment.
  2. Navigate to the Project/Shell where the issue has been observed > User Mode > Home node > Open Shell Details > Options > Note the financial period selected.
  3. Navigate to Cost Manager > Cash Flow > Open Cash Flow Node > Select the specific Cash Flow curve > Set curve to Auto by default profile per CBS and Schedule: Set "Use dates from Schedule Sheet 1", From Date=Start Date and To Date=Finish Date.
  4. Open the Cash Flow Curve, Note that there are blank dates displayed.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.