On : 11.13.20.01.0 version, Set Up Project Management

ACTUAL BEHAVIOR
Project Parallel Approval Workflow is reverting the status back to Draft
 

EXPECTED BEHAVIOR
Project status workflow to get to 'Submitted' status and go for approval to Project Manager/Approval Group

STEPS
The issue can be reproduced at will with the following steps:
1. Set the Project Parallel Approval Workflow in BPW using approval group. please see the below rule that is set in.
When setting the project to 'Submitted' status, Save and close, then the project status is getting reverted back to Draft.

Rule1:

IF 1 is 1 AND
ProjectStatusNotificationApprovalPayloadType.projectStatusApprovalEventInfo.projectStatus is "Submitted"

Than
List Builder : Approval Group
Response Type : Required
Approval Group : Project Approval Group
Allow Empty Group : Empty
Rule Name: "Rule1"

Even tried removing if condition -> ProjectStatusNotificationApprovalPayloadType.projectStatusApprovalEventInfo.projectStatus is "Submitted"

but project is status is revert back to 'Draft' status.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.