Goal

One can manually set individual review due dates beyond the cycle's due date without any validation of the relationship.  If the Plan Review Cycle has a Due Date, any due date set manually for an individual review should be the same as or sooner than the cycle's due date.

Steps:
1. Log in to PSCR as a plan review coordinator.
2. Find a permit with an open Plan Review Cycle, or start a new Cycle on a permit in Plan Review status.
3. If there is no Cycle Due Date, set one.
4. Add reviewers to the cycle if none are present already.
5. Open the details of an individual plan review and select a Due Date that is after the cycle's due date.
6. Click Save.
7. Validate whether you receive any error regarding the setting of the date beyond the cycle's due date.

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!