On Unifier : Version 20.3

When changing the Currency in the Cost Sheet from Project Currency to Base Currency:

ACTUAL BEHAVIOR
---------------
Project Currency/Base currency is not changing on the project cost sheet even though they are different.

EXPECTED BEHAVIOR
-----------------------
Project Currency/Base currency should display the difference on the project cost sheet.

Example:

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot see the difference on the cost sheet when Base Currency and Project Currency contains different values.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.