Linked Dates from Schedule Sheet are off by One Day from the Source Dates (Doc ID 2679735.1)

Last updated on JUNE 11, 2020

Applies to:

Primavera Unifier Cloud Service - Version 19.12.1.0 to 19.12.4.0 [Release 19.12]
Primavera Unifier - Version 19.12.1.0 to 19.12.4.0 [Release 19.12]
Information in this document applies to any platform.

Symptoms

On : Unifier 19.12.1

ACTUAL BEHAVIOR
---------------

The dates in Linked Date Data Elements (DE) on the Schedule Sheet roll back one day and do not match the linked data Data Elements in the source design from where they are linked from.

EXPECTED BEHAVIOR
-----------------------

The dates in the source design should match with the dates in the linked activity in the schedule sheet.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.