Master KM: Guide to Production Management and Supervisor Mobile Application (Setup, Functional Flow, FAQ, Troubleshooting) (Doc ID 2680284.1)

Last updated on AUGUST 07, 2024

Applies to:

Oracle Fusion Manufacturing Cloud Service - Version 11.13.20.01.0 and later
Information in this document applies to any platform.

Purpose

 The purpose of this document is to provide a complete guide to implementers and users on production management and supervisor mobile application on Oracle cloud.

Scope

This document will guide implementation teams and users through setups, functional flow of production management and supervisor mobile application, address frequently asked questions and help troubleshoot common issues. 

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
 Overview
 Production Management
 Work Execution
 Setups
 Master Data Setups
 Product Master Data Setups
 Work Definition
 Production Management Functional Flow
 Work Order Types
 Standard Work Order
 Non-standard Work Order
 Rework and Transform Work Orders
 Work Order Statuses and History
 Work Order Scheduling
 Forward Scheduling
 Backward Scheduling
 Midpoint Scheduling
 Efficiency and Utilization
 Work Order Operations, Operation Items and Operation Resources
 Adding Operations to Released Work Orders
 Process Manufacturing Work Orders
 Work Order Operation Outputs
 Scaling Work Orders
 Manufacturing Supervisor Mobile Application
 Downloading App
 Setting Up
 Manufacturing Supervisor Mobile Application Functional Flow
 Authentication
 Plant, Work area, Work center Selection
 Mobile App Overview (Searching a work order)
 Work Order Actions Using Mobile App
 Frequently Asked Questions (FAQ)
 Is there a linkage between work orders for parent and child items in planned orders in process manufacturing?
 Is the actual start date of work order synched with the date the work order is released?
 Is it possible to only re-schedule one operation in work order with multiple operation without impacting the prior and succeeding operation schedules?
 Why does component required date populated in FBDI to upload non-standard work order not showing up as the material required date for the component in the work order?
 How to create work order created from back to back order with unreleased status?
 Is it feasible to make it mandatory for production operator/users to enter the lot attributes while completing the work order?
 Is there any option to manage an efficiency percentage at operation level in work definition? If so, how does it impact work orders?
 Why does an item being transformed using a 'Transform Work Order' require a different serial number on completion to different items?
 Why does midpoint Rescheduling (any rescheduling of work order - forward or backward) not change the start/end date of the operation/work order?
 Does FBDI upload of work orders allow addition of adhoc resources and materials to standard operations within the work order?
 Is it feasible to modify the decimal precision for work order transactions e.g. 'Usage Rate' etc.?
 Is there a setup to round quantities for work orders generated from planning having fractional quantities due to definition of shrinkage factor in planning?
 While creating work order through FBDI though the start/end dates are populated in the FBDI template, why does the work order get created with a different date other than the one provided in the FBDI template?
 Is it feasible to generate work order with specific sub-type based on order type for back to back sales order?
 Can work order end date/start date be scheduled beyond year( 53 weeks)?
 Why does simultaneous resources that are scheduled having the same start time but different end time though the usage rate is the same?
 Can work order sub-type field be made mandatory?
 Is possible to change the start date for multiple operations of work order to start at the same time?
 Why is the supply subinventory for phantom assembly always derived from the components rather than the work definition supply subinventory for the phantom assembly?
 Is it possible to set up approvals for work orders?
 Does supply type default for operation items added for a non-standard work order?
 Is there a way variable output/finished goods can be achieved through process manufacturing?
 Are item attachments copied over to work order? Are attachments available to view, if so how to view the attachments on the items?
 Troubleshooting
 Tips for troubleshooting production management issues
 Work Order Status
 Work Order Operation, Items, Resources and Outputs
 Work Order Scheduling
 Common Issues
 Error when transacting a work order in past date prior to item effective start date
 Rework work orders cannot be released with error - Negative inventory balances are not allowed in this organization.
 Serial numbers could not be generated. Check the serial number setup. (INV-2415963)
 The subinventory is locator controlled, a locator is required. (WIE-4425149)
 Item Yield is not considered for the work order even if it is available in the work definition
 Your changes were not saved because the work order was updated by another user.
 Phantom item does not explode to show the item under its item structure in PIM when creating a work order.
 The supply line is in exception because the quantity was reduced in the execution document
 Phantom item explosion in work order are missing components
 A work definition is required for a standard work order. (WIE-4425097)
 ORA-01882: Timezone Region Not Found
 Supply Type for Phantom Items is Defaulting From Master Org Item Specifications
 The work order creation failed because there is an incomplete operation assignment in the ATO model work definition as of work definition date xxxx-xx-xx 16:53:21. (WIS-4440484)