My Oracle Support Banner

FA:SCM:CST WIP Material Standard Cost Adjustment Is Not Created As Expected (Doc ID 2683337.1)

Last updated on JUNE 25, 2020

Applies to:

Oracle Fusion Manufacturing Cloud Service - Version 11.13.20.01.0 and later
Information in this document applies to any platform.

Goal

Material issued to work order on 5/31 @$11 each
STandard Cost of component went to $12 on 6/7
Material issued to work order on 6/16 @12 each
WO Completed 6/16
WO Closed 6/16

The final product is actual costed, so it costed when the work order closed.

Expected cost: since the standard cost of the items are now $24 (2x$12), we should have received a $1 Material Standard Cost Adjustment.

why WIP material standard cost adjustment not generated for the scenario mentioned?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution