Symptoms

On : 11.13.20.01.0 version, Plan Project-Manage Project Budget

ACTUAL BEHAVIOR
Budget Status Stay same (Submitted) After last approver approve the budget

EXPECTED BEHAVIOR
Budget status must be set to 'Baselined' after approval


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Created a new budget version -> Submit for Approval -> Last approver approve the budget -> Task Completed -> The budget status stay same submitted and not changed to current baseline

On a specific project Submitted budget version : Version <n> for approval

Budget status remain stuck in 'Submitted' status.

 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.