My Oracle Support Banner

Incorrect Stored Period Earned Value Data (Doc ID 2689625.1)

Last updated on JULY 16, 2020

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8 to 18.8.2.0 [Release 18.8]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.12.0.0 to 17.12.11.0 [Release 17.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12 to 19.12.4.0 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.1 to 20.4 [Release 20.1 to 20.4]
Primavera P6 Enterprise Project Portfolio Management - Version 19.12 to 19.12.4.0 [Release 19.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Issue with the Earned Value calculation stored values. For example, one Activity, the value of this activity was earned in Oct($2,398.53), Nov($19,188.24) and Dec($2,398.53) 2017. The full $23,985.30 value for this Activity is stored across these 3 periods yet the store period performance process has added another $ 0.92 in the Feb 2018 period.

EXPECTED BEHAVIOR

The Period Expense cost is correct with the following formula: This Period Expense cost = Current Expense cost - Total of all stored This Period Expense Costs


STEPS

The issue can be reproduced at will with the following steps:

  1. View project with baseline.
  2. View Period Earned Value costs for specific time period.
  3. Update activity percent complete on an activity.
  4. Store Period Performance.
  5. Notice not all value is stored for a month in the time period.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.