Symptoms

On : 11.13.20.04.0 version, Control Project-Manage Project Forecast

ACTUAL BEHAVIOR
When viewing any Forecast or Budget the Total Sum fields are not aligned with the Detailed values. This makes reading and analyzing data very difficult.
 

EXPECTED BEHAVIOR
Detailed and total amount should be right aligned on Forecast page - Review and Finalize Forecast - section Common PRBS: Period Performance Details

STEPS
The issue can be reproduced at will with the following steps:
1. Project Financial Management - click on Project number to oepn it

2. Manage Project Forecast page
Edit Forecast: Version

3. Review and Finalize Forecast

4. Go down Expand section Common PRBS: Period Performance Details
Details amount and total amount are shifted (totals are to left, details amount are at right side) so not aligned to the right

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution