Activity Page Shows Grid View Is Selected When Gantt View Is Displayed (Doc ID 2704596.1)

Last updated on JUNE 29, 2021

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12 to 19.12.7.0 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management - Version 19.12 to 19.12.7.0 [Release 19.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Activities page shows activity table/grid selected when Gantt chart is shown on screen.

EXPECTED BEHAVIOR

The Gantt Chart should not be visible as it is not enabled.


The issue can be reproduced at will with the following steps:

  1. Log into P6 Web.
  2. Activities page.
  3. Switch from Grid to Gantt.
  4. Switch from Gantt back to Grid.
  5. Go to another page..
  6. When go back to Activities page, shows Grid enabled, but Gantt displayed.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.