PRC:PO:Split Requisition Line Button Is Dimmed in Process Requisitions Even When Budget Is Not Enabled For Requisitions & Enabled For Procurement
(Doc ID 2714703.1)
Last updated on OCTOBER 22, 2021
Applies to:
Oracle Fusion Purchasing Cloud Service - Version 11.13.20.07.0 and laterOracle Fusion Purchasing - Version 11.13.20.01.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
Split option is not enabled in Process Requisitions even when the Budget is not enabled for Requisitions & Enabled for Procurement.
EXPECTED BEHAVIOR
-----------------------
Split option should be enabled for requisition when the budget is not enabled for Requisitions.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Ensure Budget is Not enabled for Requisition and Enabled for Procurement
2. Navigate to Process Requisitions & check the Split option is Not enabled.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |