ACTUAL BEHAVIOR
---------------

The summary activity Duration takes into consideration all calendar days while all its subcategories takes only business/working days.

EXPECTED BEHAVIOR
-----------------------
The duration calculation should be consistence

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login Unifier
2. Go to Project, open Schedule Sheet.
3. The summary activity Duration takes into consideration all calendar days.



BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot see the duration as expected

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.