Level Of Effort Activities Not Calculating Correct Durations (Doc ID 2728711.1)

Last updated on NOVEMBER 19, 2020

Applies to:

Oracle Primavera Cloud Service - Version 19.9 to 20.9 [Release 19.9 to 20.9]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Level of Effort activities default to 5 days and do not calculate correctly.

EXPECTED BEHAVIOR

Expect LOE activities to calculate duration based on their relationships.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into OPC.
  2. Open project.
  3. Create LOE activity.
  4. Notice duration is not calculated correctly.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!