In P6 Professional Upper Table Views the Lag Value Displays Incorrectly When the Assigned Calendar's Hours Per Day Is Different Than Global Setting Hour Per Day (Doc ID 2728758.1)

Last updated on NOVEMBER 17, 2020

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.3 and later
Primavera P6 Enterprise Project Portfolio Management - Version 19.12.3.0 and later
Information in this document applies to any platform.

Symptoms

The upper layout column Relationship Lag values display incorrectly when the global Time Period setting 'Use assigned calendars to specify the number of work hours for each time period' is ticked on AND the assigned predecessor's calendar Hours Per Day value (e.g., 7.5) is different than the global Application Settings > Time Period > Hours per Day value (e.g., 8.0).

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.