Future Bucket Is Not Eligible For Editing Planned Unit/Budgeted Unit (ETC) (Doc ID 2729827.1)

Last updated on DECEMBER 24, 2020

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12.7.0 and later
Information in this document applies to any platform.

Symptoms

On : 19.12.7.0 version, Cloud: P6 Application

ACTUAL BEHAVIOR
---------------
When trying to "bucket load" planned hours in the Resource Assignments view, with the timescale set to months, some of the months allow entry of planned units whilst others do not.

EXPECTED BEHAVIOR
-----------------------
All month entries should allow input.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Log in to P6 Pro for EPPM.
2. Open a project and navigate to resource assignments view.
3. Try to input budgeted values for months.

BUSINESS IMPACT
-----------------------
The issue has the following business impact
Due to this issue, users cannot use the feature of resource bucket planning.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.