Duplicate Resource Assignments Are Created Upon Update of P6 EPPM XML to Oracle Primavera Cloud (OPC) Project Data (Doc ID 2765949.1)

Last updated on APRIL 02, 2021

Applies to:

Oracle Primavera Cloud Service - Version 21.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:

Duplicate Resource Assignments upon update of Migrated P6 EPPM to OPC project data.

We recently Migrated data from P6 EPPM to OPC using P6 XML Import. Now we decided to update the Resource Assignments and Activity Duration of the Migrated P6 EPPM in OPC using P6 XML. After the update, all Resource Assignments got duplicated.
 

EXPECTED BEHAVIOR:

For the Resources to not get duplicated.

STEPS:

The issue can be reproduced at will with the following steps:
1. Import P6 XML.
2. Import the same XML updating the existing Project.
3. Resources are duplicated instead of updated.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!