Is It Possible To Change The Control Budget From Advisory to Absolute?
(Doc ID 2766170.1)
Last updated on APRIL 26, 2023
Applies to:
Oracle Fusion Project Control Cloud Service - Version 11.13.21.01.0 and laterInformation in this document applies to any platform.
Goal
On : 11.13.21.01.0 version, Project Budget
Is it possible to change the Control Budget from Advisory to Absolute?
The user add Cost Budget to the Current Version and he needs to Change Budget Control level from Advisory to Absolute. After changing it with no error, when submit the Budget for Approval , encountered error :
"The proposed project control budget level Absolute isn't supported."
Solution
To view full details, sign in with your My Oracle Support account. |
|