Symptoms

They have a scheduled jobs for restructure that was created in 2018 that is
no longer working as a scheduled job. If they run the same job but as "Run
Now" it works and the restructure is done. If they create a new scheduled
restructure job it also works. However, they want to keep this scheduled job
as it was created in 2018 by the client.

Example:
The scheduled job ran on March 20, it ran successfully but did not perform
the restructure. It shows the next job to run on March 27. They want to
know how can the date can change when the restructure was not done. It gives
a false impression that it completed.



Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.