Milestone Imported Incorrectly From Microsoft Project XML (Doc ID 2772558.1)

Last updated on JULY 13, 2021

Applies to:

Oracle Primavera Cloud Service - Version 21.1 to 21.4 [Release 21.1 to 21.4]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When importing a Microsoft Project XML, a milestone activity is converted to a Resource Dependent zero duration activity.

EXPECTED BEHAVIOR

Expect activity to remain a milestone.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into OPC.
  2. Open a workspace and import MSP XML.
  3. Notice milestone activity in MSP is now a Resource Dependent zero duration activity in OPC.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!