FA: SCM: GOP: How To Force Global Order Promising (GOP) To Consume Supply From On-Hand Balance Once Sales Order Enters Available to Promise (ATP) Time Fence
(Doc ID 2785137.1)
Last updated on JULY 29, 2021
Applies to:
Oracle Fusion Global Order Promising Cloud Service - Version 11.13.21.04.0 and laterInformation in this document applies to any platform.
Goal
How to Force GOP to Consume Supply from On-Hand Balance once Sales Order Enters ATP Time Fence without performing Re-scheduling
For non Back-to-Back items in GOP Promising.
Currently when a Sales Order is created with Request Date outside the ATP Time Fence (set at 7 days) and an item has lead times less than that (example 4 days),
the order is scheduled based on the lead times and consumption is not reflected in Review Supply Availability.
Is there a way to configure GOP so that orders that come inside the ATP Time Fence consume On-Hand quantities automatically without UNSCHEDULE / RESCHEDULE ?
Steps to Reproduce:
1. Non Back-to-Back Item with 4 days of Total Lead Time and ATP Time Fence Parameter set to 7 days (User-Defined)
2. On-Hand available and no other sales orders present to consume supply for that item
3. Create Sales Order 8 days in the future ( 1 day outside ATP Time Fence) and see that order is scheduled with
Request Date = Ship Date -1 (with 1 day of transit time for carrier)
4. After Order is created, the Consumption is not reflected in GOP Review Supply Availability
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |