Budget Missing For December When Curve Assigned on a Cash Flow Chart (Doc ID 2787963.1)

Last updated on JUNE 30, 2021

Applies to:

Oracle Primavera Cloud Service - Version 21.5 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When using Cash Flow and assigning a curve, budget skips the month of December.

EXPECTED BEHAVIOR

Expect budget to be applied in December according to assigned curve.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into OPC.
  2. Open a project.
  3. Cash Flow.
  4. Assign curve and prorate over the year. Budget skips December.

 