Error: 'Calendars can be assigned to projects, resources/roles, or both. You must remove these assignments before you can change the Available To setting on the calendar (PRM-006015006) (PRM-001003233) when Integrating with P6 (Doc ID 2797579.1)

Last updated on AUGUST 06, 2021

Applies to:

Oracle Primavera Cloud Service - Version 21.2 and later
Information in this document applies to any platform.

Symptoms

When running on-premise P6 integration errors are returned:

ERROR
-----------------------
CALENDAR with ID -100 for action CREATE is failing with the error Calendars can be assigned to projects, resources/roles, or both. You must remove these assignments before you can change the Available To setting on the calendar. (PRM-006015006) (PRM-001003233)

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create OPC Project with same name as P6 Project.
2. Integrate OPC Project with P6 Project => error returned.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.