My Oracle Support Banner

Error: "You are not assigned to the following activities. Reload this timesheet to see your current assignments." When Saving or Submitting Timesheet (Doc ID 2808675.1)

Last updated on OCTOBER 21, 2021

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 21.6 to 21.9 [Release 21.6 to 21.9]
Information in this document applies to any platform.

Symptoms

After a user removes an activity from a timesheet that he has been removed as a resource assignment from in P6, when he tries to save or submit a timesheet, sees error:

ERROR

"You are not assigned to the following activities. Reload this timesheet to see your current assignments."

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into Team Member | Timesheets.
  2. Open active timesheet.
  3. Remove activity from timesheet.
  4. Save changes or add hours and submit.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.