My Oracle Support Banner

EV Sheet (CBS Option) Not Calculating ETC (Doc ID 2816920.1)

Last updated on OCTOBER 26, 2021

Applies to:

Primavera Unifier Cloud Service - Version 19.12.8.0 to 20.12.6.0 [Release 19.12 to 20.12]
Information in this document applies to any platform.

Symptoms

On : 19.12.8.0 version, Unifier Application

ACTUAL BEHAVIOR
---------------
The ETC on the EV Sheet (CBS Option) is calculating incorrectly.

EXPECTED BEHAVIOR
-----------------------
ETC value should be calculated correctly.

STEPS
-----------------------
The issue has been reproduced using the following steps:

  1. Open the impacted Project.
  2. Open Earned Value Analysis.
  3. Double click on the EV Sheet.
  4. Select the CBS option from the drop-down menu.
  5. Select the CBS selector.
  6. Select all CBS nodes.
  7. Select Apply.
  8. The ETC is calculating incorrectly.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.