Updating a P6 Activity Calendar and Performing 'Send to Unifier Schedule Sheet' Using the 'Merge' Option Does Not Update the Schedule Sheet Activity Calendar (Doc ID 2816955.1)

Last updated on JANUARY 10, 2022

Applies to:

Primavera Unifier Cloud Service - Version 19.12 to 21.10 [Release 19.12 to 21.10]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Updating P6 activity calendar and 'Send to Unifier Schedule Sheet' with Merge option does not update Schedule Sheet activity calendar.

EXPECTED BEHAVIOR

The Schedule Sheet activity calendar should be updated.

 

The issue can be reproduced at will using the following steps:

  1. Create example 'Calendar 1' and 'Calendar 2' in both P6 and Unifier.
  2. Import P6 activities to Unifier Schedule Sheet - activity A100 created with 'Calendar 1' assigned.
  3. Activity A100 with 'Calendar 1' assigned is created in Schedule Sheet.
  4. In P6, change A100 to have 'Calendar 2' assigned.
  5. With Unifier Data Mapping > Option set to Merge, Send Activities from P6 to Schedule Sheet (legacy integration).
  6. Schedule Sheet A100 is not updated with new 'Calendar 2' assignment; 'Calendar 1' is still assigned.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!