ACTUAL BEHAVIOUR
-------------------------------
Maximum Escalation level for cost center manager supervisor hierarchy is set as 1, but task getting assigned to higher levels, once the first level escalation owner approves

EXPECTED BEHAVIOR
-------------------------------
Task should not be assigned to higher levels, once first level escalation owner approves

STEPS
----------
1. Customer has set Maximum Escalation Level to 1 for ReqApproval task in BPM
2. Approval rule is based on Cost Center Manager Supervisor hierarchy, with Number of Approval Levels as 1
Start with is also Cost Center Manager (for example name is "X")
3. PR created and tree generated as per approval hierarchy defined. PR submitted
5. Line manager hierarchy is X < Y < Z < A
6. If X approves, PR gets approved as expected. But if X does not approve then gets escalated to Y, also expected
7. Y does not approve, task gets expired as expected.
8. But if Y approves, the task is getting escalated to Z. This is unexpected



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.