ACWP Showing In-Period Instead of Cumulative on the EV Sheet - CBS Option (Doc ID 2819356.1)

Last updated on NOVEMBER 04, 2021

Applies to:

Primavera Unifier Cloud Service - Version 19.12.8.0 to 20.12.8.0 [Release 19.12 to 20.12]
Primavera Unifier - Version 19.12.8.0 to 20.12.8.0 [Release 19.12 to 20.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
On the Earned Value (EV) Sheet (Cost Breakdown Structure Option) the Action Cost of Work Performed (ACWP) is showing in-period instead of cumulative.

The Estimate to complete (ETC) is calculating in-period and not cumulatively.

EXPECTED BEHAVIOR
-----------------------
The ETC should be calculating cumulatively.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login into Unifier.
  2. Open a Project.
  3. Open Earned Value Analysis.
  4. Double click on the EV Sheet.
  5. Select the CBS option from the drop-down menu.
  6. Select the CBS selector.
  7. Select all CBS nodes.
  8. Select Apply.
  9. Notice that the ETC is calculating in-period and not cumulatively.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!