Goal
Portfolio Manager Question
When changing configuration field in Portfolio Manager, all projects have to be unlinked and relinked to the portfolio in order for the change to be seen.
Can there be a better way to update the current Portfolio Manager to accept the change and not have to manually unlink and relink all the projects?
Solution