Project Cost Sheet Displaying Incorrect Amount in a Column Where Formula Equals 'Sum of All Rows' (Doc ID 2854066.1)

Last updated on MARCH 21, 2022

Applies to:

Primavera Unifier Cloud Service - Version 21.3 to 22.3 [Release 21.3 to 22.3]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
A Project Cost Sheet is displaying an incorrect amount in a column that uses a Commit-type Business Process (Approved) as the Data Source.

Example:

Line 75 | Cost Code: 12-00000-000 | Equipment and Furniture
  -> Approved Commitments: $632,353.75
  -> When adding up the line items with a manually, the total is actually: $635,028.14

EXPECTED BEHAVIOR
-----------------------
The 'Approved Commitments' formula is = Sum of All Rows. All rows should be added together correctly.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login as a user with access to the Project Cost Sheet.
  2. Navigate to the impacted Project/Shell.
  3. Open the Cost Sheet.
  4. Observe the total amount in the column.
  5. Add up the values in the Column manually and compare the amounts.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution