Cash Flow Fails To Plot Curves When the Start and End Dates Are From the Activity Sheet (Doc ID 2856302.1)

Last updated on MARCH 17, 2022

Applies to:

Primavera Unifier Cloud Service - Version 21.12 to 21.12.1.0 [Release 21.12]
Primavera Unifier - Version 21.12 to 21.12.1.0 [Release 21.12]
Information in this document applies to any platform.

Symptoms

On Unifier : Version 21.12

When the Cash Flow Curves are configured to have the Start and End dates plot/populate from the Activity Sheet:

Expected Result

All curves should plot/populate with the applicable dates when the Start and End dates are coming from the Activity Sheet.

Actual Result

The Cash Flow fails to plot the Actuals and Forecast curves when Start and End dates are from the Activity Sheet. However the Baseline will plot.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References