Dependent Activity Doesn't Match Time Changes When Importing Schedule
(Doc ID 2868961.1)
Last updated on MAY 12, 2022
Applies to:
Primavera Unifier Cloud Service - Version 20.12.9.0 to 21.12.2.0 [Release 20.12 to 21.12]Primavera Unifier - Version 20.12.9.0 to 21.12.2.0 [Release 20.12 to 21.12]
Information in this document applies to any platform.
Symptoms
When attempting to import a schedule, if the User tries to reduce the time for an activity, the dependent activities will not also decrease in time.
The time for an activity/dependent activity will adjust properly when it is manually created instead.
STEPS TO REPRODUCE:
- Go to schedule manager.
- Schedule sheets.
- Try to import a schedule.
- Reduce the time for an activity.
- Observe that it does not decrease in time for the dependent activity.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |