After XER Import and F5 Refresh (Before Scheduling or Modifying Any Data) Resource Assignment Duration Recalculates and No Longer Equals Activity Duration (Doc ID 2874554.1)

Last updated on FEBRUARY 08, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8 and later
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 and later
Information in this document applies to any platform.

Symptoms

Why does resource assignment duration change after creating a new project during XER import then selecting F5 refresh, which occurs before scheduling or modifying any project or activity data?

ACTUAL BEHAVIOR

In P6 Professional after XER import completes, then if F5 refresh is selected will update the resource assignment duration and making it different than the activity's duration.

EXPECTED BEHAVIOR

In P6 Professional after XER import completes, then if F5 refresh is selected should not update the resource assignment duration, making it different than the activity's duration.

STEPS

The issue can be reproduced at will with the following steps:

1. Login to P6 Professional.
2. Import XER and Create New Project with resource assignments
3. From Activities page, display lower Resources tab and F5 refresh
4. Result: the resource assignment duration is updated, making it different than the activity's duration (see illustration below):

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!