Applies to:
Oracle Retail Merchandising Foundation Cloud Service - Version 19.3 and laterInformation in this document applies to any platform.
Goal
Discrepancy in loaded PO data via spreadsheet.
When trying to load a PO with approved(A) status, it’s getting loaded with "worksheet(W) status" in ordhead.
Also, written_date in ordhead is not populating the correct date provided in spreadsheet. It is taking "22-Feb-2022" as written_date.
Estimated instock date is taking ’22-Feb-2022’ in ordloc, whereas in spreadsheet Estimated instock date value passed is null.
Solution